Construction

Photo Gallery

Click the links below to view the album from each build site.  Albums will be continuously updated, so please check back often.

 

Crosby Elementary

Harrison Elementary

Harrison Junior School

Miami Whitewater Elementary

 

May, 2020

At Harrison Elementary,  The stage bearing walls have been completed and the masons have moved to the gym, kitchen, and mechanical walls in Area A. In Area B, Steel is being set in sequence #2 while the metal decking gets installed in sequence #1. Electrical and plumbing rough-ins are being installed in bearing block.

At Crosby Elementary,  Bearing walls in Area A begin to rise with the start of the gym. The stage and cafeteria walls have been laid out this week. In Area B, steel in sequence #1 is being set with metal decking closely behind. Electrical and plumbing rough-ins are being installed in bearing block.

At Miami Whitewater Elementary,  Bearing walls in Area B continue to rise in preparation for steel sequences #1 and #2. The site has been prepped for the delivery of steel and the crane. Electrical and plumbing rough-ins continue in Area B. The installation of the gas main across the MWW Elem and the Junior High site continues. 

At Harrison Junior School,  The concrete footers in Area C will be complete this week followed by the foundation block in Area B . Underground electric and plumbing is being installed across all 3 areas. In Area A, the East half of the slab on grade was poured last week and the West half will be poured this week. 


Weekly Blitz - 05/01/20

Weekly Blitz - 05/08/20

Weekly Blitz - 05/15/20

Weekly Blitz - 05/22/20

 

April, 2020

At the elementary schools, slab-on-grade pours continue, bearing walls continue to rise, and exterior MEP (mechanical, electrical, plumbing) work continues. Steel work is underway at Harrison El., with Crosby and Miami Whitewater soon to follow.

At the middle school, foundation and footer work are underway, with primary electrical conduit being installed as well.  Underground plumbing work is in progress.  The first slab on grade pour happened at the end of April.  

Weekly Blitz - 04/03/20

Weekly Blitz - 04/10/20

Weekly Blitz - 04/17/20

Weekly Blitz - 04/24/20



March, 2020

At Miami Whitewater, concrete footings are finished.  CMU (Concrete Masonry Unit) installation has begun, and the first slab pour will happen soon.  The parking lot between the buildings has also been stabilized. 

At Crosby and Harrison El., bearing walls continue to rise, slab on grade pours continue, along with underground MEP (Mechanical, Electrical, Plumbing) installation, and underground kitchen utilities continue to progress. 

The Junior High has kicked off with the start of the concrete footers in Area A. The primary electric and site communication feed continue across the site. Logistics gravel has also been placed.

Weekly Blitz - 03/06/20

Weekly Blitz - 03/13/20

Weekly Blitz - 03/20/20

Weekly Blitz - 03/27/20

 

February, 2020

At Crosby and Harrison El., footers are complete and foundation block is being laid.  Underground utility prep / slab prep is getting underway.  Masons and electricians have been mobilized.  Elevator pits are in process.  Bearing walls have begun to rise. 

At Central Campus, storm piping is complete and aggregate piering is taking place.  The water main has been brought into the site, and footers are expected to start up by early March.


Weekly Blitz - 02/07/20

Weekly Blitz - 02/14/20

Weekly Blitz - 02/21/20

Weekly Blitz - 02/28/20

 

January, 2020

Installation of utility piping for water distribution continues, gravel laydown continues, exterior footings and foundations are underway. Storm water drainage is complete at Harrison and Crosby. The loop road gravel is installed at central campus, the north parking lot and junior school east parking lot is graveled in.  350 Geopiers are being installed at central campus.  Both the new Junior School and Miami Whitewater Elementary will sit on these piers, due to their weight and the ground underneath the schools being sand and gravel. 

 

Weekly Blitz - 01/10/20

Weekly Blitz - 01/17/20

Weekly Blitz - 01/24/20

Weekly Blitz - 01/31/20



December, 2019

Storm piping and drainage has been installed at all three sites, and stone and cement stabilization is complete.  Footers will be installed next month and additional utilities and concrete pads follow the footers.  Work with the engineers continues for the necessary road improvements at Crosby and Miami Whitewater.  Working in concert with the City of Harrison and Hamilton County, we were awarded a combination grant for over $800K for our Central Campus road work – which will result in turn lanes near the tennis courts on West Road and a turn lane near the condos on Dry Fork Road.  There will also be the first round-about in Harrison coming to the intersection of Dry Fork and West Road.  Road improvements will take shape towards the very end of our project. 


Weekly Blitz - 12/06/19

Weekly Blitz - 12/13/19

Weekly Blitz - 12/20/19



November, 2019

Dirt continues to move, with the areas where the schools will sit being at their proper levels. Detention ponds are finished with the necessary piping. Storm drainage and utilities are being worked on. Cement stabilization is complete and footers are expected to start taking shape around November 15. Utilities and concrete pads follow the footers.

A technology meeting was held on November 6, speaking to what the classroom / building tech will include, as well as camera surveillance, swipe card door entries, wiring installs, panic buttons, etc.

An important piece to our new schools (and renovated High School) is telling our story through our Pride Wall project. The fourth Pride Wall committee meetings were held on November 5 & 6.  Connecting our rich history with the future is extremely powerful, and these meetings continue with this endeavor. At this latest round of meetings, we nailed down our final template, started to piece together what our walls will look like and made some critical decisions with regards to continuity and flow. We also talked “finish line” and additional picture / memorabilia collection.  Meeting notes can be found HERE.


Weekly Blitz - 11/08/19

Weekly Blitz - 11/22/19

Weekly Blitz - 11/29/19



October, 2019

Early site work began in earnest in early October, 2019.  This included removing current obstacles, earth moving, and site preparation.  



September, 2019

The third meeting of the Pride Wall Committee was held on September 17.  At this meeting, each of the four site committees met together to continue to refine the plan.  Many photographs and artifacts have been obtained, with more continuing to roll in.  A more definite dimension of space was now available, which aided in the prioritization of the items to be included.  Meeting notes can be found HERE.